From signing to the second sale in about 26 months, starting from a plot that is ready to build on.
Two separate buyers means two separate exits. The first sale repays the loans and most of the investor's capital.

| Stage | Months | What happens | Who |
|---|---|---|---|
| Agreement | 0–1 | Joint development agreement and power of attorney registered; the advance paid; the architect appointed | Owner, investor, lawyer |
| Design and approvals | 1–6 | Final drawings, TCP technical clearance (with the 20 % relaxation), the village panchayat construction licence, the bank's sanction | Architect, owner |
| Foundations and plinth | 6–8 | Setting out, excavation, footings, laterite plinth | Contractor |
| Structure | 8–13 | RCC frame and slabs for the ground, first and attic floors, the stair and lift shaft | Contractor, structural engineer |
| Roof and envelope | 13–15 | 45° roofs and Mangalore tiles, walls, window frames and glazing | Contractor |
| Services and finishes | 14–19 | Electrical, plumbing, lift, flooring, plaster and paint, kitchens and baths | Contractor, specialists |
| Pools and landscaping | 18–21 | Pools, decks, courts, gates, hedges and planting | Pool and landscape contractors |
| Completion | 21–22 | Snagging, utility connections, occupancy certificate | Architect, owner |
| Sales | From structure-complete to 26 | Marketing starts once the structure is up; each villa is registered to its buyer after the occupancy certificate, so no GST applies | Owner, broker |
Months from signing. Construction runs about 16–18 months; the two villas are built together.